HURON — A Huron contractor will start this year’s milling and paving work at 7 a.m. Monday.
The city has identified more than a dozen areas of town to be included in the project.
Asphalt Paving & Materials Co. will place no parking signs the day before it begins operations on each street. Any vehicles on the street at the start of the work will be towed at the owner’s expense.
The streets will be blocked off during the actual milling and paving.
Milling will be done from May 1 through May 5. Paving will be done May 8 through May 19, weather permitting.
Those with a sump pump that drains into a street being paved are asked to reroute it immediately to the back yard, and leave it there until the street is finished.
Sprinkler systems should not be in use during this time frame, as it will help expedite the paving process. The streets must be dry before they can be paved.
Here are the areas of town to be milled and paved in the $851,396 project: